36 apartments on a quay, assembled in eleven days
Four-storey rental building for a municipal housing company. Modules produced over nine weeks while the quay wall and foundation were rebuilt; crane work took eleven working days; tenants moved in 27 weeks after contract.
“The factory photos every Friday meant our board never asked whether we were on schedule.”Project director, municipal housing company (placeholder quote, case study to be confirmed)